CMC recently completed work onboard the YC-1537 Barge with undocking taking place on November 28, 2016. There work onboard the barge consisted of 2 phases.1st Phase – Afloat Work. Period of Performance: August 01, 2016 – August 31, 2016. Work performed included Gas Free Services, Cargo Tank Inspections, Main Deck, Port and STBD Sides, and Hazardous Waste Removal. 2nd Phase – Drydock Work. Period of Performance: October 12, 2016 – November 30, 2016 (undocked Nov 28th). Work performed included Underwater Hull Repair, Inspection of Hull Zinc Anodes, and Ultrasonic Hull Gauging.